Blackout-Readyby Crisis-Ready Society

Home / The guide / Sanitation

Sanitation · Approvals, site and separation distances · sanitation-5

Have the site and soil evaluated

Soil decides whether a drainfield can work. A soil and site evaluation (often including a percolation test or soil profile) shows how fast water soaks in and how deep the seasonal water table and bedrock are.

How

  1. Use the site survey from the site module to pick candidate areas: away from wells, watercourses, steep slopes and places where water collects.
  2. Book the soil evaluation or percolation test required by your authority. It is often done by a licensed evaluator or the authority itself.
  3. Ask for the evaluation in the wettest season if possible, so the seasonal high water table is seen.
  4. US EPA notes that a conventional drainfield relies on roughly 2 to 4 feet of unsaturated soil under it to treat effluent. Shallow soil or high groundwater points to mound, sand filter or other advanced options.
  5. Legal minimums differ. Example, Washington State (USA): at least 36 inches (0.9 m) between the bottom of the drainfield and the seasonal high water table or a restrictive layer, reducible to 24 inches only with advanced pre-treatment and extra studies.
  6. Identify a second suitable area as a reserve for a future replacement drainfield, as US EPA recommends.
  7. Mark and fence off the chosen areas so no vehicles compact them during construction.

Safety: Soil test pits can collapse. Never enter a deep pit that is not shored or benched.

Do these first

Sources

  1. Decentralized Systems Technology Fact Sheet: Septic Tank Soil Absorption Systems (EPA 932-F-99-075). US Environmental Protection Agency, accessed 2026-11
  2. Types of Septic Systems. US Environmental Protection Agency, accessed 2026-11
  3. WAC 246-272B-06100 Vertical separation. Washington State Legislature, accessed 2026-11