Land and site · Civil works on site · site-17Install access and erosion controls first
Before major digging, build a basic construction track and put erosion and sediment controls in place, so the first storm does not wash the site away.
How
- Check whether you need a construction stormwater permit. Example (US): disturbing 1 acre or more (or less, if part of a larger plan that will disturb 1 acre) needs Clean Water Act permit coverage, which usually means filing a notice of intent, writing a stormwater pollution prevention plan, maintaining controls and inspecting them. Your state or EPA region issues it; other countries have their own rules.
- Rough in the driveway alignment and a stabilised entrance (crushed rock) so trucks do not track mud.
- Install silt fences or wattles on contour below disturbed ground, and diversions above it.
- Fence off trees to keep and the septic area, so machinery does not compact the soil there.
- Set up a material laydown area on high, flat ground.
Safety: Keep people well clear of operating machinery.
Do these first
Sources
- Site and Soil Evaluation for Onsite Wastewater Systems (MF2645). Kansas State University Research and Extension, accessed 2026-11
- Low-Volume Roads Engineering Best Management Practices, Chapter 5: Hydrologic Analysis. USDA Forest Service, accessed 2026-11
- Stormwater Discharges from Construction Activities. US Environmental Protection Agency, accessed 2026-11
- Stormwater Phase II Final Rule Fact Sheet 3.0: Small Construction Program Overview. US Environmental Protection Agency, accessed 2026-11