Permits and budget · Phase and schedule the build · legal-14Build a schedule and find the critical path
The critical path is the longest chain of dependent tasks from start to finish, and so it sets the earliest possible finish date (GAO). A delay on any task in that chain delays the whole project, so it is where your attention must go.
How
- List every task from your phasing plan with an estimated duration, including permit decision times and inspection waits.
- Mark which tasks depend on others. A typical off-grid chain: land purchase, then permits, then access road, then foundations and buried services (water, wastewater, cables), then shell, then roof, then systems, then inspections, then occupancy.
- Draw the tasks as a simple chart or use free scheduling software and find the longest chain of dependent tasks: that is the critical path.
- Put each inspection hold point from design-20 in the schedule as a task with its own waiting time.
- GAO suggests also checking the longest path (the chain that actually drives a key date) because software flags can mislead when you fix dates by hand.
- Long lead items often sit on it: permit decisions, well drilling slots, battery and inverter deliveries, custom windows.
- Order long lead items early and book specialist trades well ahead.
- Add weather allowances to outdoor tasks (see climate notes).
- Be wary of squeezing the schedule: GAO guidance notes that accelerating work can cut short-term cost but often raises long-term cost.
- Update the schedule weekly during the build.
Do these first
Sources